WWTP construction for Pepsico - Marbo

PROJECT DESCRIPTION

Veolia Water Solutions & Technologies is contracted to design and construct an adaptation and improvement of the existing wastewater treatment plant at the Pepsico - Marbo factory in Bački Maglić. The deadline for the execution of the works is 5 months. The scope of work is the preparation of a conceptual solution, procurement, delivery, installation, testing and commissioning of the equipment.

WORKS DESCRIPTION

Works of Veolia Water Solutions & Technologies d.o.o. Belgrade on the reconstruction and extension of the primary treatment of the existing WWTP Marbo Product d.o.o. includes:

  1. Reconstruction and extension of the system for removing sand and solid waste from wastewater.
    Removal is performed with a combined device through a system of automatic coarse sieves and sandboxes with automatic screening, sand evacuation and automatic removal of dried sand into a container.
  2. Installation of screw compactor.
  3. Replacement of the existing rotating screen with a suitable system of higher capacity.