PROJECT DESCRIPTION
Tender Reference: SWUP III (Subotica Water Upgrade Project III)
Project Number: 7742-IFT-43472
Contract Signing Date: August 17, 2017
Commencement Date: October 23, 2017
Time for Completion: 880 days
Defects Notification Period: 365 days
WORKS DESCRIPTION
Construction of WTP consist of folowing:
- Rehabilitation of existing wells by delivery of new well pumps
- Design and construction of one or more de-sanding units to catch the sand from the wells and pre-ozonization
- Design and construction of one water treatment plant building for a design capacity of 160 l/s and construction of first stage treatment capacity of 80 l/s/s
- Design review/adaptation and construction of a clear water tank of 2,500 m³
- Design review/adaptation and construction of a high pressure pumping station for 200 l/s for a maximum pressure of 6.0 bars
- Design and construction of sludge treatment line with sludge thickening and dewatering, and supernatant re-use
- Delivery and installation of an atomic absorption spectrophotometer AA-7000/AAC unit with graphite flame hybrid technique and auto sampler with auto atomizer changer with wavelenght range: 180.0 to 900.0 nm, vehicles and other auxiliary works
LOCATION:
Subotica, Serbia
INVESTOR:
JPUC Waterworks and Sewerage Subotica
TYPE OF THE PROJECT:
Conditions of Contract for Plant and Design-Build (FIDIC Yellow Book)
CONTRACT VALUE:
5.550.075,79 €
EXPECTED COMPLETION OF WORKS:
March 2020.